Kimou (Southwest - Qingshen) Surface Treatment Circular Economy Industrial Park Capping of Phase I Main Construction

Kimou (Southwest - Qingshen) Surface Treatment Circular Economy Industrial Park Capping of Phase I Main Construction

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2022-05-17
  • Views:0

(Summary description)On 13 May, as the construction work of Kimou (Southwest - Qingshen) Surface Treatment Circular Economy Industrial Park celebrated its first anniversary, the main construction of the three centers of wastewater treatment, wind control and thermal power as well as 10 standard factory buildings came to the capping stage.

Kimou (Southwest - Qingshen) Surface Treatment Circular Economy Industrial Park Capping of Phase I Main Construction

(Summary description)On 13 May, as the construction work of Kimou (Southwest - Qingshen) Surface Treatment Circular Economy Industrial Park celebrated its first anniversary, the main construction of the three centers of wastewater treatment, wind control and thermal power as well as 10 standard factory buildings came to the capping stage.

  • Categories:Company News
  • Author:
  • Origin:
  • Time of issue:2022-05-17
  • Views:0

On 13 May, as the construction work of Kimou (Southwest - Qingshen) Surface Treatment Circular Economy Industrial Park (hereinafter referred to as "Qingshen Park") celebrated its first anniversary, the main construction of the three centers of wastewater treatment, wind control and thermal power as well as 10 standard factory buildings came to the capping stage.

 

Wastewater Treatment Centre

 

The wastewater treatment center is the core construction work of Phase I of the park, with a main building area of approximately 32,000 square meters and a wastewater treatment capacity of 5,000t/d, including chemical, biochemical, reuse and sludge treatment systems, which can collect and centralize the 16 types of industrial wastewater produced by the surface treatment enterprises in the park and realize the recycling of wastewater and achieve the discharge standard.

 

Construction of the auxiliary wind control and thermal power center, as well as the building of dangerous chemicals are undergoing simultaneously.

 

1

 

Standardized Factories

 

Phase I of the construction of 10 standard factories with a total construction area of 110,000 square meters is scheduled to be completed and delivered in June and August this year respectively, which can meet the demand of more than 40 surface treatment enterprises to move in.

 

1

 

Since Phase I construction work has started in May 2021, Qingshen Park has been pushing forward the construction of the project on the basis of strict implementation of various environmental protection and epidemic prevention measures, so as to ensure the safe and controllable quality of the project, and the construction work of equipment installation, process adjustment, decoration and gardening in the later phase will continue in an orderly manner to ensure the full completion of Phase I construction works, and smoothly welcome the opening of the park and production in December this year.